Time Machine
Drag through eight weeks of construction. Compare weeks side by side, overlay them, or let the change map highlight what moved. Then record observations — with evidence — for your report.
Week 4: Slab complete, Level 1 steel up, tower crane on site, steel staged west, new annex pad east of the building. → Week 6: Metal roof deck on, south and west walls complete, east wall started, parking base graded. (Summaries are ground truth for the demo only — in the field you won’t have them.)
Observation or interpretation?
“Asphalt covers the west half of the parking area in week 7; the east half is still gravel.”
“The roof deck will be finished next week.”
“The steel crew is ahead of schedule.”
“They must have used the stockpile for backfill.”
“The drainage design is bad.”
“The stockpile in grid G-1 is visibly smaller than in week 3.”
“Steel columns are visible across the full footprint in week 6; none were visible in week 4.”
“Standing water is visible in the southwest corner of the excavation.”